How long before you can walk, drive or put furniture on new concrete?

It's the first thing almost everyone asks once the truck pulls away. Concrete doesn't go from wet to done all at once. It gets stronger in stages over about a month, so the answer depends on what you want to do with it.

Concrete finishers screeding a freshly poured slab

The short version

What you want to doAbout how long to wait
Walk on it24 to 48 hours
Bikes, wheelbarrows, kids playingAbout 3 days
Patio furniture and the grillAbout a week
Park a regular carAbout a week
Heavy trucks, RVs, trailers, dumpstersAbout a month (28 days)

Those are rough numbers for normal weather. Cold slows everything down, so in late fall or winter we'll usually tell you to add a few days.

It's curing, not drying

People say concrete "dries," but that's not really what's happening. The cement reacts with the water in the mix and slowly hardens, and that reaction actually needs moisture to keep going. If a fresh slab dries out too fast, the reaction stops early near the surface and you end up with a weaker top layer that's more likely to crack, dust or flake.

Concrete reaches roughly 70 percent of its design strength in about a week and keeps gaining for weeks after that. Twenty-eight days is the number engineers use for "full strength," which is why that's the wait for anything heavy.

Concrete finishers screeding a freshly poured slab
Fresh concrete right after it's placed. The next few days decide how strong the surface ends up.

Why it's trickier here

Colorado Springs is dry, sunny and sits above 6,000 feet. On a July afternoon with a breeze, the top of a slab can lose moisture fast. That's why we're careful about when we pour (early morning in the summer) and why we use a curing compound or keep the surface damp for the first few days.

In fall and winter it's the opposite problem. We'll use warm water or an accelerator in the mix and cover the slab with insulated blankets when nights drop below freezing.

If you've got new concrete and the forecast says hot and windy, a light misting with the hose in the morning and evening for the first few days won't hurt. Just don't blast it.

A few things to avoid the first year

  • Don't drive or park right along the edges early on. Edges are the weakest part of a slab.
  • Don't use rock salt or ice melt the first winter. Throw sand down instead. (More on that in our winter prep post.)
  • Don't let a landscaper's skid steer or a dumpster delivery roll onto a new driveway before the month is up.
  • Watch the sprinklers. A little water is fine, but fertilizer overspray and iron in some water can stain fresh concrete.

Planning a pour and want to know what the timing would look like for your job? Call or text (719) 402-0690.